Social Monitoring Report3rd Monitoring Report January 2015VIE: Power Transmission Investment Program, Tranche 2 - 500kV Pleiku-My Phuoc-Cau Bong Trans VIE: Power Transmission Investment Program, Tranche 2 – 500kV Pleiku-My Phuoc-Cau Bong Transmission Line (Dak Lak Province) smission Line (Dak Lak Province)Prepared by the Central Vietnam Power Projects Management Board for the National Power Transmission Corporation and the Asian Development Bank.This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of VIE: Power Transmission Investment Program, Tranche 2 – 500kV Pleiku-My Phuoc-Cau Bong Transmission Line (Dak Lak Province) ADB's Board of Directors, Management, or staff, and may be preliminary in nature.In preparing any country program or strategy, financing any project,VIE: Power Transmission Investment Program, Tranche 2 – 500kV Pleiku-My Phuoc-Cau Bong Transmission Line (Dak Lak Province)
or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intenSocial Monitoring Report3rd Monitoring Report January 2015VIE: Power Transmission Investment Program, Tranche 2 - 500kV Pleiku-My Phuoc-Cau Bong Trans VIE: Power Transmission Investment Program, Tranche 2 – 500kV Pleiku-My Phuoc-Cau Bong Transmission Line (Dak Lak Province) CTS MANAGEMENT BOARDPLEIKU - MY PHƯOC - CAU BONG 500 KV TRANSMISSION LINE PROJECTTHIRD MONITORING REPORTINDEPENDENT MONITORING ON RESETTLEMENT AND ETHNIC MINORITYDAK LAK PROVINCE42005NATIONAL POWER TRANSMISSION CORPORATIONCENTRAL VIETNAM POWER PROJECTS MANAGEMENT BOARDPLEIKU - MY PHUOC - CAL BONG 50 VIE: Power Transmission Investment Program, Tranche 2 – 500kV Pleiku-My Phuoc-Cau Bong Transmission Line (Dak Lak Province) 0 KV TRANSMISSION LINE PROJECTTHIRD MONITORING REPORTINDEPENDENT MONITORING ON RESETTLEMENT AND ETHNIC MINORITYDAK LAK PROVINCEPROJECT OWNERCentral ViVIE: Power Transmission Investment Program, Tranche 2 – 500kV Pleiku-My Phuoc-Cau Bong Transmission Line (Dak Lak Province)
etnam Power Projects Management BoardIMPELEMENTATIONInvestment Consultancy and Technology Transfer Co.. LtdDeputy General DirectorLE CHI CƯONG42005TABSocial Monitoring Report3rd Monitoring Report January 2015VIE: Power Transmission Investment Program, Tranche 2 - 500kV Pleiku-My Phuoc-Cau Bong Trans VIE: Power Transmission Investment Program, Tranche 2 – 500kV Pleiku-My Phuoc-Cau Bong Transmission Line (Dak Lak Province) /. /. Project overall..........................................71.1.2.Scale and scope of the Project.............................71.2.Objectives of independent monitoring..........................91.2./. Objectives of independent monitoring....................91.2.2.Monitoringlocation............... VIE: Power Transmission Investment Program, Tranche 2 – 500kV Pleiku-My Phuoc-Cau Bong Transmission Line (Dak Lak Province) .........................91.2.3.Monitoringissues..........................................9Social Monitoring Report3rd Monitoring Report January 2015VIE: Power Transmission Investment Program, Tranche 2 - 500kV Pleiku-My Phuoc-Cau Bong TransSocial Monitoring Report3rd Monitoring Report January 2015VIE: Power Transmission Investment Program, Tranche 2 - 500kV Pleiku-My Phuoc-Cau Bong TransGọi ngay